Yorkshire Brewery Progress Update 2

Progress Update 2 – Pilings

With demolition works now completed all attention has turned to the construction of the development. The first step is to construct and excavate the basement which covers most of the site. Two piling rigs were floated onto the site to commence the basement permitter piling which involves drilling out 600-700mm bored piers to the depth of the basements and then inserting reinforced steel cages into the hole and then filling with concrete. All bored piers are then finished off with a top capping beam which outlines the extent of the perimeter of basement. Next excavation of the soil and the construction of the basement walls are to be completed.

https://youtu.be/E-ViVFslJss

https://vimeo.com/93239983

 

For more information on this exciting development please contact Nina Mizzi on (03) 9650 3722.